    Construction of Cisumdawu Toll Continues to Progress

    https://www.jabarprov.go.id/En/assets/images/berita/gambar_80141.jpg

    BANDUNG - The process of building the Cileunyi Sumedang Dawuan toll road or Cisumdawu progress continues to experience positive progress. West Java Regional Secretary Iwa Karniwa explained that from all phases namely safe 1, 2, and 3 from day to day there was significant progress.

    "In phase one even the progress has been 100 percent both in terms of land acquisition and physical development or construction," said Iwa at Gedung Sate, Friday (6/21/2019).

    While for phase 2, land acquisition reached 92.2%, physical 68.62%. Phase 4 of land is 68.53%, physical is 31.1%.

    "The obstacles that still exist today are land acquisition owned by Perhutani and the existence of waqf land. However, both of them are in the process of completion, hopefully soon it will be completed," he said.

    With this good progress, Iwa hopes that the construction of the Cisumdawu toll road can be completed in 2020 and can shorten the travel time to Kertajati airport and become a means of increasing or growing economies in the area it passes. (Even)