    West Java Bogor-Ciawi-Sukabumi Toll Pushed the Acceleration of Land Acquisition

    https://www.jabarprov.go.id/En/assets/images/berita/gambar_5883.jpg

    BANDUNG-West Java Provincial Government to ensure will accelerate the process of land acquisition in section I and II toll Bogor-Ciawi-Sukabumi (Bocimi).

    Acting (Pj) Governor of West Java Moch. Iriawan said it will help accelerate a number of national strategic infrastructure projects one of them acceleration Bocimi toll section I Ciawi-Cigombong which in August targeted to be completed. "The four months is short, but I have a priority scale," he said in Bandung on Thursday (21/6/18).

    According to him Bocimi toll must be pushed acceleration because access to South West Java currently constrained. Number of complaints travelers who are ambushed long traffic jam from Sukabumi to Bogor shows the importance of this toll to be completed. "I want an acceleration of Bocimi Toll, we'll see to the field of development," he said.

    In the same place, the Regional Secretary of West Java Iwa Karniwa ensures the affairs of the land should be an important concern considering the target section I is getting closer. He recorded before Idul Fitri day, section I along the 15 kilometers of land acquisition is still left in the area of Bogor City and Bogor Regency.

    "Only 0.50% is not free yet. For the land that has not been free there are still about 26 fields or about 8,716 square meters. This is in the city of Bogor and Bogor regency, "he said.

    He explained a number of unfinished problems such as one overlapping field of land, the owner of which is complex about the area in one area, until there is one area that returns the compensation money and 10 fields are still negotiating. "August section I is scheduled to finish, but this achievement depends on the remaining land acquisition," he explained.

    To accelerate the remaining land, his side claimed to have coordinated with the Regional Land Agency (BPN). The petition, especially at BPN Bogor, is expected to help speed up the compensation in the field. "We will coordinate again the August target, but we hope this toll road can move faster," he said.

    Section I own physical current has reached 90.18% where there is a deviation of 0.47% of the target. Physical is currently focusing on building 39 bridges underpass and overpass where as many as 33 bridges have been completed. "The process is still built 6 bridges, 4 of which are over-pass bridges," he said.

    West Java provincial government, according to him, remains optimistic that toll road business entities and local governments will rush to pursue this matter. "Next we coordinate with Sukabumi regency related to land acquisition in section II and III," he said.

    From the data owned, Cigombong-Cibadak section II land progression of land acquisition has reached 60% even though physically land that freed in this section only reach 20,63% or 305 field from plan of liberation along 1,160 fields. "The release can be done quickly because the budget is no problem," he explained.

    While in section III and IV, currently recorded still not 100% free from the needs of 1821 fields. Iwa claimed to have asked Sekda Sukabumi to fully assist the land acquisition process. According to the efforts that began from now, it will be parallel to the physical completion process performed by the BUJT.

    Previously President Joko Widodo ensures, if the toll Bocimi operate then the congestion on the national side will be happening. "Ciawi-Cigombong, we wait for July to finish, until Cibadak 2019 and until Sukabumi completed 2020," said Jokowi to the press on the sidelines of review Bocimi Toll Project in Cigombong, Sukabumi, Sunday (8/4/18).